SERVING MINNEAPOLIS / ST. PAUL / MINNESOTA
Donate Now Sustaining Member

MinnPost thanks these major sponsors:




Sponsor of
Second Opinion



Our major advertisers


Our in-kind partners


MinnPost thanks these generous donors:

INDIVIDUALS AND FOUNDATI0NS
Blandin Foundation
Otto Bremer Foundation
Bush Foundation
Sage & John Cowles
David & Vicki Cox
Toby & Mae Dayton
Jack & Claire Dempsey
Ethics and Excellence in Journalism Foundation
Sam & Stacey Heins
John S. and James L. Knight Foundation
Joel & Laurie Kramer
Lee Lynch & Terry Saario
Martin & Brown Foundation
The McKnight Foundation
The Minneapolis Foundation
The Saint Paul Foundation
Rebecca & Mark Shavlik

(See all donors here.)

D.C. Dispatches by Derek Wallbank

  • Switch to Small Text Size
  • Switch to Medium Text Size
  • Switch to Large Text Size
Email Print Submit a Comment

    Peterson battling logistics on Red River flood retention plan

    By Derek Wallbank | Published Fri, Sep 3 2010 8:53 am

    Rep. Collin Peterson
    Rep. Collin Peterson

    WASHINGTON — Six months from Thursday, plans for how to store one million acre-feet of water during spring flooding will be finalized. The funding mechanisms will be identified, start dates will be decided and the legislative language needed to make it all happen will be outlined, if not fully drafted.

    That language, along with an authorization for around $500 million in federal dollars (half of the $1 billion needed), will be inserted into the next Farm Bill early in 2011 and passed sometime in 2012. Every year for the next 10, some of the hundreds of projects to be completed will be finished and the Red River of the North will annually crest 10 feet lower, reducing the flood risk from catastrophic to manageable from below Moorhead all the way downstream to the Canadian border.

    That's the plan, anyways.

    Rep. Collin Peterson, Sen. Amy Klobuchar and North Dakota Rep. Earl Pomeroy met Thursday in Moorhead to start that process with a listening meeting and press conference. The goal, Peterson said, is to "get people to understand what we're doing" and "get all these ideas on the table."

    The table, and what's on it
    One idea Peterson hopes to use is called tiling. Think of it as a giant external French drain, where a perforated pipe runs under the ground to channel water away. "You can store twice as much water underground as you can above ground," Peterson said.

    He'd also like to harness existing lakes to hold more water. The lakes would be lowered by six inches to a foot in the fall, then allowed to build up water levels to as much as a foot above normal levels.

    The more controversial sister scheme to that would be to do much the same thing but on existing wetlands. Drains would be installed to allow for control of water that could be drained in the fall and kept in the spring.

    "It's just a matter of getting everything that's out there on the table," he said.

    To that point, Peterson is soliciting suggestions he doesn't necessarily like.

    One of those comes out of the University of North Dakota, where researchers there have proposed something called the "waffle plan." It's a bit complicated, but basically involves using existing roads and smaller culverts as levees.

    Sen. Amy Klobuchar
    klobuchar.senate.govSen. Amy Klobuchar

    Let's say there are rural roads (built up several feet above the surrounding farmlands) connected in a 16-mile square. Water would be allowed to flow into the middle of that and held into place by the roads.

    Peterson said he's "not a huge fan" of the waffle plan because of concerns that the roads could be washed out — but he said he's willing to consider it as an option.

    Ultimately, hundreds of these sorts of projects will be combined to complete the retention project — but only if Peterson, Klobuchar and their allies can get all the stakeholders on board.

    Confusion breeds controversy
    There are two concurrent plans to lower the water levels on the Red River.

    Diversion is the controversial one. A second channel would be built around the city of Fargo that would act as a ring river during floods, channeling 35,000 cubic feet of water per second around the Fargo-Moorhead area and, according to estimates from city leaders there, reduce huge floods to fightable levels.

    The diversion would be built from back to front, and it wouldn't be "turned on" so to speak until everything was ready to go in an effort to reduce the risk of diverting water to areas that aren't ready to handle it.

    But the $1.4 billion plan has met with opposition from those whose land would be taken to build the diversion, as well as those downstream concerned about the extra diverted water flooding their towns.

    Peterson's plan is separate yet concurrent. The problem is that residents all along the Red River from Fargo-Moorhead on north generally don't know the difference. At a town hall meeting in his district last week, Peterson was confronted by a questioner concerned by his retention plan who illustrated her point by listing grievances she had with the diversion.

    That's worrying, he said, because plans this intricate require broad support.

    "If we're going to make this happen, we've got to pull together," Peterson said. "We can't have anybody working across purposes."

    Washington Bureau | Fri, Sep 3 2010 8:53 am | 3 Comments

    Like what you just read? Support high-quality journalism in Minnesota by becoming a member of MinnPost.

    Advertisement:

    3 Comments: Hide/Show Comments

    E-mail address

    Password

     

    Forgot Password? | Register to Comment

    MinnPost does not permit the use of foul language, personal attacks or the use of language that may be libelous or interpreted as inciting hate or sexual harassment. User comments are reviewed by moderators to ensure that comments meet these standards and adhere to MinnPost's terms of use and privacy policy.

    We intend for this area to be used by our readers as a place for civil, thought-provoking and high-quality public discussion. In order to achieve this, MinnPost requires that all commenters register and post comments with their actual names and place of residence. Register here to comment.


    Illustration by Hugh Bennewitz

    minnpost.com/derekwallbank


    Derek Wallbank is MinnPost's Washington, D.C., correspondent, covering Minnesota's congressional delegation and reporting on developments out of Washington that are important to Minnesota readers. After graduating from Michigan State University, he covered Michigan politics for the Gongwer News Service, a publication aimed at political insiders. Later he became a reporter for the Lansing State Journal, writing about education and politics and founding the Journal's respected politics blog. Most recently he was a researcher and reporter with Congressional Quarterly in Washington, D.C. He can be reached at dwallbank[at]minnpost[dot]com.